Horace, ND – Cub Creek Development CHALLENGE The Cub Creek Development in Horace faces significant challenges as the City continues to grow... Read More
Wayzata, MN – Stormwater Pond Design Enhancement & Wetland Restoration A homeowner enhanced their wetland and stormwater pond by restoring native vegetation and adding a fountain... Read More
Grafton, ND – Flood Risk Reduction Moore Engineering successfully completed a flood risk reduction project for the City of Grafton, North Dakota. Read More
Lakeville, MN – Foxborough Stormwater Pond The Moore Engineering's Environmental and Water Resources sectors worked together to complete a stormwater system to... Read More
Redpath Impoundment Flood mitigation project in Traverse and Grant Counties in Minnesota. Moore Engineering proudly served the Bois... Read More
Casselton, ND – Water Tower Replacement Challenge The City of Casselton had a 100,000-gallon multi-column water tower constructed in the early 1920s... Read More
Verndale, MN – Water Treatment Plant & Supply Wells Challenge The city of Verndale, Minnesota had been pulling water from two wells since the 1960s,... Read More
Buffalo/Lynchburg, ND Ditch Retrofit Challenge The Buffalo-Lynchburg Channel had received minor, infrequent maintenance since its construction in 1961. This natural... Read More
Lakeville, MN – Stream/Channel Restoration Challenge Middle Creek, a tributary of the Vermillion River in Dakota County, Minnesota, suffered from issues... Read More
Lake Traverse Water Quality Improvements (TCD 52) Challenge Traverse County Ditch 52 (TCD 52) is an open channel tributary that discharges into Lake... Read More