Mapleton, N.D. – School Zone Improvements (11/20/17 Update) The project is substantially complete and small items remain to be completed. The final lift of... Read More
Otter Tail County, Minn – Lake Outlet Project (11/20/17 Update) Construction contracts are signed and contractors have started. The site for the pump station is cleared... Read More
Otter Tail County, Minn. – Lake Outlet Project (10/10/17 Update) The bid letting for the project was held on October 3, 2017 and construction is expected... Read More
Lisbon, N.D. – Sheyenne River Flood Protection (9/22/17 Update) The contractor has finished concrete work and asphalt paving on 4th Avenue and Rose Street. The... Read More
Glen Ullin, N.D. – Street and Utility Improvement (9/19/17 Update) TRAFFIC CONTROL • Traffic in the alley between E Street and F Street has increased. Through-traffic,... Read More
Arthur, N.D. – Water Main Replacement (9/8/17 Update) The original scope of work is complete on the project. Bids came in lower than expected,... Read More
Mapleton, N.D. – School Zone Improvements (9/1/17 Update) Concrete work is being completed and asphalt is scheduled to be put down very soon. The... Read More
Lisbon, N.D. – Sheyenne River Flood Protection (8/28/17 Update) Construction is continuing as planned for Levee D. The underground utilities portion of the project is... Read More
Mapleton, N.D. – School Zone Improvements (8/3/17 Update) The contractor is finishing the underground utility installations and should finish early next week. There is... Read More
Arthur, N.D. – Water Main Replacement (8/3/17 Update) Underground and asphalt work is complete, including seal coating. Minor items remain on the project, but... Read More