Lisbon, N.D. – Sheyenne River Flood Protection (8/28/17 Update)

Construction is continuing as planned for Levee D.

The underground utilities portion of the project is completed on 4th Avenue and Rose Street. The contractor is currently installing the gravel for the streets and the concrete curb and gutter in this area. Asphalt Paving will begin shortly for 4th Avenue and Rose Street.

The concrete footings are completed on north portion of floodwall. The contractor is working on constructing forms and pouring sections of the north floodwall. Concurrently, they are pouring concrete footings for the south floodwall and removable stop log structure.

The project is scheduled for completion by November 24th.  Thank you for your patience during construction.