Hector Water Treatment Plant 11/24/15 Update The plant was startup and placed back into service near the end of October. Doors and... Read More
Hector Wastewater Treatment Plant 11/24/15 Update The floors, walls, and roof of the new process treatment building are complete. Piping, pumping, and... Read More
Hector Wastewater Treatment Plant 10/23/15 Update The concrete walls for the new biosolids storage tank are complete. The aeration and mixing equipment... Read More
New England Infrastructure 10/20/15 Update The water main has been completely replaced along with the water services. All of the water... Read More
Hector Wastewater Treatment Plant 10/20/15 Update The new process building foundation and first floor concrete work is complete. The masons have begun... Read More
Hector Water Treatment Plant 10/20/15 Update The contractor has bypassed the water treatment plant to allow work on the gravity filter. Work... Read More
Maple River Dam 10/20/15 Update The project is currently 95 percent complete and the contractor is completing the placement of the earthen... Read More