Glen Ullin, N.D. – Street and Utility Improvement (9/19/17 Update)
TRAFFIC CONTROL
• Traffic in the alley between E Street and F Street has increased. Through-traffic, please detour around the site using F Street.
PROGRESS REPORT
• Watermain installation from Main Street to C Street was completed last week.
• Pressure testing and bacterial testing is underway. Once the tests pass, the temporary water will be disconnected and services will be attached to the improved water system.
• Storm sewer installation at all three intersections was rescheduled for this week.
• Subgrade excavation for curb and gutter areas is in progress and curb and gutter installation is scheduled for this week.