TRAFFIC CONTROL
• Traffic in the alley between E Street and F Street has increased. Through-traffic, please detour around the site using F Street.

PROGRESS REPORT
• Watermain installation from Main Street to C Street was completed last week.

• Pressure testing and bacterial testing is underway. Once the tests pass, the temporary water will be disconnected and services will be attached to the improved water system.

• Storm sewer installation at all three intersections was rescheduled for this week.

• Subgrade excavation for curb and gutter areas is in progress and curb and gutter installation is scheduled for this week.