Hector Water Treatment Plant 11/24/15 Update The plant was startup and placed back into service near the end of October. Doors and... Read More
Hector Wastewater Treatment Plant 11/24/15 Update The floors, walls, and roof of the new process treatment building are complete. Piping, pumping, and... Read More
FEMA levee certification reduces need for flood insurance It’s fall. The ground is frosty in the morning. Those once-beautiful, turning leaves are now on... Read More
Jim Brownlee hired as a Municipal Administration Specialist Moore Engineering recently hired Jim Brownlee as a municipal administration specialist. In his role, Brownlee will... Read More
Hector Wastewater Treatment Plant 10/23/15 Update The concrete walls for the new biosolids storage tank are complete. The aeration and mixing equipment... Read More
Are you ready for your next transportation project? Safe, reliable transportation is vital for every community. But how does a county decide when a... Read More
Cooperation key to building Upper Maple River Dam WEST FARGO, N.D. – As eastern North Dakota continues to work on limiting the impact of... Read More
New England Infrastructure 10/20/15 Update The water main has been completely replaced along with the water services. All of the water... Read More
Hector Wastewater Treatment Plant 10/20/15 Update The new process building foundation and first floor concrete work is complete. The masons have begun... Read More
Hector Water Treatment Plant 10/20/15 Update The contractor has bypassed the water treatment plant to allow work on the gravity filter. Work... Read More