Otter Tail County, Minn. – Lake Outlet Project (5/23/18 Update)

Contractors have installed the intake structure and a 10-foot by 10-foot pressure sustaining structure along 450th Street, along with about 80 percent of the forcemain for the project. Concrete footings for the pump station are complete. The pump station is roughly 35 percent done, with an expected completion date in mid-July. Please remember to respect … Read More

Otter Tail County Lake Outlet Project (4/24/18 Update)

The traffic detour in place has closed 410th Ave. for construction and is anticipated to remain closed through the first week of May. Contractors began installing 24-inch forcemain pipe along 410th Ave. and have installed 1,700 feet of pipe from the common leg junction to the cemetery.  At this point, approximately 10 percent of the forcemain has … Read More

Otter Tail County, Minn – Lake Outlet Project (1/4/18 Update)

The precast concrete wet well at the pump house site was installed, then backfilled and sealed for winter. In addition, portions of the forcemain, intake pipe and backwash line were installed. Three of the wells for dewatering at the pump house site have been removed. Dewatering on the pump station site is finished for the winter. … Read More

Otter Tail County, Minn – Lake Outlet Project (11/20/17 Update)

Construction contracts are signed and contractors have started. The site for the pump station is cleared and they will be starting de-watering operations.  The de-watering system will hopefully discharge into Little McDonald Lake prior to the lake freezing. If it isn’t completed by freeze, the area will be marked because of unsafe ice conditions. In … Read More