News

Back to News

Otter Tail County, Minn. – Lake Outlet Project (5/23/18 Update)

Contractors have installed the intake structure and a 10-foot by 10-foot pressure sustaining structure along 450th Street, along with about 80 percent of the forcemain for the project.

Concrete footings for the pump station are complete. The pump station is roughly 35 percent done, with an expected completion date in mid-July.

Please remember to respect the construction personnel and process by avoiding the construction area if possible.

Powered by MHP.SI
Top