Otter Tail County, Minn – Lake Outlet Project (1/4/18 Update)

The precast concrete wet well at the pump house site was installed, then backfilled and sealed for winter. In addition, portions of the forcemain, intake pipe and backwash line were installed. Three of the wells for dewatering at the pump house site have been removed. Dewatering on the pump station site is finished for the winter.

Tree removal operations from the pump house to 450th Street will be ongoing throughout the winter. All other work will continue in the spring.