Hector, Minn. Water Treatment Plant 2/25/16 Update
The water treatment plant is substantially complete pending minor closeout work.
Hector Water Treatment Plant 11/24/15 Update
The plant was startup and placed back into service near the end of October. Doors and windows were replaced. The control systems were tested and the plant was placed into automatic operation. Remaining work consists of cleanup, touchup, caulking, sealing and painting.
Hector Water Treatment Plant 10/20/15 Update
The contractor has bypassed the water treatment plant to allow work on the gravity filter. Work on the filter and high service pump replacement has begun. The contractor has sandblasted the old paint, cleaned the filters and disposed of old filter media. The new underdrain and interior components of the filter have been installed. The … Read More