Gladen Construction plans to begin de-watering operations the week of April 10. On Monday, April 17, they will fully mobilize into town with five crews (four underground crews to finish digging in the 5 blocks of sanitary sewer, along with various storm sewer around town, and one gravel/road crew to prep completed roads for paving). 

Knife River Concrete, the subcontractor doing concrete work, will move onto site on April 24. They will follow the road crew throughout town to do their work. Asphalt paving will take place later this summer.

Final completion is set for late July 2017.