Category: LaMoure Sewer Improvements

LaMoure, N.D. – Sewer Improvements (6/12/17 Update)

The sanitary sewer replacement is completed and the contractor is working on reconstructing the streets. Almost all of the new curb and gutter is installed and the asphalt paving on the north half of town (north of the railroad tracks) is complete. The contractor will continue preparing roads and paving the next few weeks on the south … Read More

LaMoure Sewer Improvement (4/12/17 Update)

Gladen Construction plans to begin de-watering operations the week of April 10. On Monday, April 17, they will fully mobilize into town with five crews (four underground crews to finish digging in the 5 blocks of sanitary sewer, along with various storm sewer around town, and one gravel/road crew to prep completed roads for paving).  Knife River Concrete, the … Read More