July 19, 2024
The asphalt milling and overlaying will occur at the end of July in Newport Ridge Phase 1 along with the paving of Sheyenne Street. We are working to get more definite dates from the contractor. Signs will be set in boulevards in advance to warn residents of the schedule and impacts. The contractor is to provide seeding, weed control, and watering for the turf reestablishment areas, and that work is to be performed before the end of August.
June 11, 2024
Concrete removals and replacements will begin the week of Monday 6/17 and continue for the following 2 weeks in Newport Ridge Phase 1. Concrete removals and replacements include impacts to some driveways. The Contractor will communicate to residents with specific access impacts.
May 10, 2024
Construction activities have begun in the Newport Ridge – Phase 5 project location (new development) with the closure of Prairie Parkway and site preparation for earthwork and underground utility installation.
May 1, 2024
Construction activities are expected to start as soon as possible, pending funding approval.