Fargo, N.D. – Block 9 Site Design The conceptual engineering and architectural plans have been presented to the City of Fargo and we... Read More
Finley, N.D., Industrial Park Sewer & Water Extension – 7/27 Update Contractors recently paved the sewer and water extension. Project will come to completion after minor remaining work... Read More
Hector, Minn – Wastewater Treatment Plant – 7/27 Update The wastewater plant is nearing completion with substantial completion date of August 3rd. Most of the... Read More
Fargo, N.D. – NDSU Water, Sewer, Storm Sewer – 7/26 Update Contractors have finished paving. This week, they are striping the pavement and seeding. Read More
The learning curve behind the modern roundabout Since the early 2000s, roundabouts have had Fargo-Moorhead-West Fargo motorists driving in circles. With their growing... Read More
Fargo, N.D. – NDSU Water, Sewer, Storm Sewer – 7/13 Update Concrete paving of the road is in progress. Read More
Fargo, N.D. – NDSU Water, Sewer & Street Improvements – 7/8 update All underground utilities have been completed except for sanitary sewer cured-in-place pipe (CIPP) lining. The contractor... Read More
Lysne named N.D. Young Engineer of the Year Kurt Lysne, PE, CFM, was recently named North Dakota’s 2015 Young Engineer of the Year by... Read More
Upper Maple River Dam 6/7/16 Update A dedication and ribbon cutting ceremony for this project is planned for June 21, 2016 at... Read More
Always There It’s National Public Works Week. Maybe you’ve seen the poster in your workplace. With the theme,... Read More