Hector, Minn Wastewater Treatment Plant 2/26/16 Update

Doors have been installed and replaced on the new and existing treatment buildings. Piping in the new process treatment building was completed. The stairway serving the process treatment building has been set. New RAS pumps were set and connected. UV equipment was set and is being prepared for service. HVAC equipment is being set and electrical work is beginning.