Lisbon, N.D. – Sheyenne River Flood Protection (8/28/17 Update)

Construction is continuing as planned for Levee D. The underground utilities portion of the project is completed on 4th Avenue and Rose Street. The contractor is currently installing the gravel for the streets and the concrete curb and gutter in this area. Asphalt Paving will begin shortly for 4th Avenue and Rose Street. The concrete … Read More